We think we’re finally done with everything we had to get done before concrete. The Glavel is in and compacted, the filter fabric is laid on top, and the Stego radon barrier is installed under the building slab. Every one of the 22 (!) conduits and pipes has been meticulously sealed with mastic.
Tomorrow morning our concrete contractor will form for the two slabs and add rebar, and concrete for the first slab is due at 10am. Fingers crossed!